How often should I review a PUWER assessment?

Factory Worker

According the PUWER Acop L22, a PUWER inspection should be performed:

​

  • After installation and before being used for the first time.

  • After assembly at a new location / site

  • At suitable intervals (this depends on the machine, the assessor will advise, generally 3-5 yearly is acceptable)

  • After being exposed to conditions which may jeopardise the safety of the equipment (e.g. after a flood and the equipment gets wet (when it shouldn’t), or following a FLT collision with the equipment.

  • Following an accident on the machine / equipment.

​

The frequency really does depend on the equipment and the conditions its being operated in, for example an external conveyor belt on a dusty aggregates site may need to be reviewed 2 or 3 yearly, but a conveyor indoors, in lab conditions, may receive a review frequency of 5-7 years.

​

​

​

​